Item Coversheet

City of Marquette, MI
300 West Baraga Avenue
Marquette, MI 49855


Agenda Date: 10/14/2025

Consent Agenda
Peg Hirvonen Bandshell - Construction Contract Change Order

BACKGROUND: 

At the April 14, 2025 meeting, the City Commission awarded the construction bid for the Peg Hirvonen Bandshell to Miron Construction Co., Inc., in the amount of $2,084,175.  

 

There have been two change orders to date resulting in an addition of $13,496.27 to the contract.

 

Miron has requested a third change order in the amount of $2,557.93 for a total contract amount of $2,100,229.20.  This change order addresses additional electrical needs in the back-of-house.

 

City Band has committed to raising all of the funds for this project and has recommended the City approve this change order.


FISCAL EFFECT: 

Marquette City Band has committed to raising all additional funds resulting in no general fund contributions by the City. 


RECOMMENDATION: 

Approve Change Order three in the amount of $2,557.93 and authorize the City Manager or her designee to sign it.


ALTERNATIVES: 
As determined by the Commission.

ATTACHMENTS:
Description
Change Order 3