Consent Agenda Sidewalk Repair, Extension and Safety Improvements Project |
| | | | | | | | | BACKGROUND: | Plans have been developed for a construction bid package which includes the extension of sidewalks along Wright Street, pedestrian safety signage, and replacement of sidewalks at various locations that are deemed trip hazards or that are causing drainage issues. The project was advertised for bids and three contractors responded. The Engineer's estimate for this project was $105,338.80. The bid results are summarized below.
| Contractor |
Bid |
Premeau Construction Inc.
|
$92,463.00
|
Arrow Constructions
|
$98,571.50 |
Associated Constructors
|
$129,627.28 |
|
|
| | | | | | | | | FISCAL EFFECT: | | Funds for this project are approved in the FY 2023 budget. |
|
| | | | | | | | | RECOMMENDATION: | | Approve a contract for the Sidewalk Repair, Extension and Safety Improvements project with Premeau Construction Inc. in an amount not-to-exceed $92,463.00 based on the quantities and unit prices bid, allow the City Manager to use a 15 percent contingency for any unknown circumstances, and authorize the Mayor and Clerk to sign the Contract. |
|